Here are the highlights from the August 15th construction progress meeting detailing the contractor's activities that are occurring on the GGB addition project:

·  The standing seam roof has been installed on the sides of the skylights.  Work will begin on the west wall and penthouse roofs within the next week.

·  Penthouse louver installation continues.

·  Electrical feeder cables are being pulled into the penthouse electrical panels.

·  Exterior stone is 85 % complete on the north side and 60% complete on the east side.

·  Mechanical, electrical and plumbing rough-ins continue on the 2nd and 3rd levels.