Highlights from the March 27th Construction Progress Meeting

Here are the highlights from the March 27th construction progress meeting detailing contractor activities that are underway for the GGB addition project.

1st level
   * continue finish paint
   * continue installing door frames and doors
   * continue lab case work and Mechanical/Electrical/Plumbing (MEP) connections
   * continue install of ULV chambers
   * install lighting in the Galleria
   * complete balance of the cove base
   * begin cleaning of all surfaces

2nd level
   * finish paint soffits at Galleria
   * continue install of glass handrails
   * prep floors and continue terrazzo flooring
   * install vanity countertops
   * continue M/E/P finishes
   * continue installing lab casework and MEP connections
   * install devices and cover plates

3rd level
   * finish paint Galleria
   * finish painting continues in labs
   * M/E/P work continues
   * begin terrazzo flooring
   * continue to install lighting and devices
   * continue to prep and install terrazzo flooring (90% complete)
   * installing casework on the west side

Penthouse
   * start and check equipment
   * continue mechanical piping to units

Site/General
   * field measured for panels at E and W canopy entrances.  They will be shipped on April 21st.
   * develop sequence to complete the site work

The current substantial completion date has been established as June 4th.  Furniture will be install during May.  Move in of the occupants will occur in June and July.

Make sure to check the CoE FMO web site at www.engin.umich.edu/facilities for updated photos of the construction.

 

  • John Keedy 
    Director of Facilities 
    College of Engineering 
    734/647-7158 
    jakeedy@umich.edu 
  • Kim Fineis 
    Facilities Administrative Assistant 
    Michigan Engineering 
    (734) 647-7070 
    kcfineis@umich.edu 
Comments