Highlights from the January 16th Construction Progress Meeting

Here are the highlights from the January 16th construction progress meeting detailing contractor activities that are underway for the GGB addition project.

·  Final painting is underway on all floors.

·  Ceramic tile is being installed in toilet rooms on levels 1 & 2.

·  Lighting is being installed in ceilings of levels 1 & 2.

·  Doors and frames are being installed on level 1.

·  Flooring in the labs on level 1 is almost complete.

·  Casework installation is underway in the labs on the 1st level.

·  The glass handrail in the galleria in underway.

·  Equipment start-ups are underway - HHW pumps, ChW pumps, air compressors, etc.

·  the new substation has been activated and the temporary power has been switched to the permanent power

Make sure to check the CoE FMO web site for the live web cam as well as updated photos of the construction site.

 

Make sure to check the CoE FMO web site for the live web cam as well as updated photos of the construction site.

 

  • John Keedy 
    Director of Facilities 
    College of Engineering 
    734/647-7158 
    jakeedy@umich.edu 
  • Kim Fineis 
    Facilities Administrative Assistant 
    Michigan Engineering 
    (734) 647-7070 
    kcfineis@umich.edu 
Comments